Inserting, Deleting, and Moving Tasks with Custom WBS Codes
You should stabilize your WBS and your schedule
before adding the custom WBS codes so that you do not have to spend too
much time making changes to them. On occasion, however, you will find
that you need to add or delete tasks and perhaps move entire work
packages to different areas of your WBS. Project makes some automatic
numbering changes, and you need to be aware of how these changes work
if you use custom WBS codes.
When you insert a new task into a work package
(summary task group), Project automatically gives it the next highest
codes for the level. If you delete a task, Project renumbers the tasks
that follow. If these are not the behaviors that you want, you will
need to manage the addition and deletion carefully.
If you move a task to another row within a work
package, it keeps its original code even though it will no longer be in
sequence. If you move a task from one work package to another (not a
recommended practice), it acquires the correct prefix code for the new
work package. The final part of the code may change if it would be a
duplicate of an existing task within the package.
Editing Custom WBS Codes
Editing custom codes after the code mask is created
is straightforward. Select a summary task by double-clicking any field
in the row except the row number. The Summary Task Information window
appears. Because you have created a WBS code mask, under the Custom
Fields tab, a custom field called WBS should be visible. Select the
value field for WBS. Make your change in the entry bar immediately
above the custom field name list box.
You will be editing only the last segment of any of
the custom codes; all the higher-level segments are derived from the
higher levels (summary task levels). You can change the segment codes
at the summary task level if the assignment made by Project does not
fit with what your organization would like to see.
For instance, in Figure 4,
the major phases have been edited as abbreviations or acronyms for the
name of the phase. AA was the default WBS code for the Planning the
Move phase, but it has been changed to PLAN. It makes it easier to
realize a task’s place within the WBS code.
If you want to show the tasks in their WBS code
order, select the View tab, Sort, Sort By and then select the WBS field
in the Sort By box.
You lose your edited codes if you edit custom codes
for summary tasks and then tell Project to renumber the tasks. Use the
following steps to prevent that from happening:
1. | Using the Gantt view, select the Format tab.
|
2. | Clear the Show Summary Tasks check box. Only the normal and milestone tasks should be displayed.
|
3. | Choose one of the column headings to select all displayed tasks.
|
4. | Select
the Project tab, WBS, Renumber to bring up the WBS Renumbering dialog
box (if Renumber is grayed out, a custom WBS code mask has not been
created).
|
5. | Click the Selected Tasks button instead of the Entire Project button.
|
6. | Click OK to begin renumbering.
|
7. | You
can then restore the display of summary tasks by selecting the Format
tab, Show Summary check box. Click any cell to unselect all tasks.
|
Your entire task list will be displayed again. Your
summary tasks have not lost their edited codes, but all of your other
tasks have been renumbered to the current order of the outline.
Renumbering the Custom WBS Codes
As
you are planning your project, you are likely to revise the task list
somewhere along the line. If you have already defined the custom WBS
codes by this time, they might not be in sequence after the editing.
Microsoft Project will recalculate the WBS codes for the whole project,
putting them into sequence for you. Follow these steps to renumber the
WBS codes:
1. | If
you are only renumbering a small, selected set of tasks, choose those
tasks first (they must be adjacent to one other). The first selected
task will not be renumbered, but will be the starting point for
renumbering the rest of the selection.
|
2. | Go to the Project tab, WBS, Renumber to pull up the WBS Renumbering dialog box, shown in Figure 5.
|
3. | Pick either Selected tasks or Entire project.
|
4. | Click OK to begin renumbering.
|
5. | If you decide to renumber the whole task list, Project will ask you to confirm your decision. Click Yes or No as necessary.
|
If, even with a warning to confirm your decision,
you still end up realizing that you did not want to renumber, you can
go back and use the Undo feature to restore your original codes.