Microsoft Project 2010 : Tracking Your Project Progress - Working with Project Baselines (part 1) - Viewing Baselines

3/29/2015 9:08:52 PM

The principal thing to remember when preparing to the base line your project is that neither the project nor the base line is crowned.  As much as you might like to think that your project is perfect, conditions will change—usually things outside your control. It is because of these changes that you need to baseline; using the baseline helps you to track these changes. Although you should always make sure to keep a copy of your original baseline, as you make changes to the project, you can use one of the additional ten baselines to keep track of the changes.

According to PMI’s PMBOK Guide, a baseline is defined as “the original plan, plus or minus approved changes.” Setting a baseline enables you to use variance and earned value analysis to later understand how the work is performed and whether the project is proceeding according to plan.


Viewing Baselines

Microsoft Project provides several methods to view baseline and tracking data. Each task and resources assignment contains many types of information such as task name, duration, work, cost, start and finish dates, and so forth. When you select the Project tab, Schedule, Set Baseline, Project copies key parts of the task and assignment data into special baseline fields.

Project has several predefined combinations of view, table, groups, and filter settings to let you review task and assignment baseline data. You can also create and store your own combinations of views and tables that show you information in a familiar format. For instance, you can do the following:

  • Use the default views and tables to see baseline columns with additional columns you need.

  • Activate filters and groups to show important baseline and tracking data based on task completion status, assigned resources, and so forth.

Consider using the following helpful viewing combinations to review baseline and tracking information:

  • View the default Tracking Gantt with the Baseline table to see baseline columns with Gantt bar overlay showing plan vs. baseline duration.

  • View the Detailed Gantt with Delay table to see task slippage and free slack.

  • View the Multiple Baseline Gantt if you are comparing several baselines side-by-side.

  • View the default Tracking Gantt with the Variance table to show differences between the baseline and your current progress conditions.

  • View the default Tracking Gantt with the Tracking table to see the data field where you can enter progress information, such as: actual start, %Complete, actual work, and so forth.

  • Select the View tab and then Group by Complete and Incomplete Tasks.

Tip

Remember that your current view of your project’s schedule data can be modified in a variety of ways, including the More Views selection underneath the Gantt Chart or Task Usage controls or the Filter, Group By, and Tables controls on the View tab. These tricks enable you to organize information and also see settings or options that might be hidden.


Figure 1 illustrates the combination of Tracking Gantt with the Baseline table. You can add your own data columns, such as: work, % Complete, physical % complete, and so forth to suit your needs. Notice how any task that does not have baseline data will show “NA” in the data field and also show missing bars within the Tracking Gantt view. Also notice how the baseline Gantt bars might be shifted to the past or future, compared to the current task start and finish dates.

Figure 1. Use View and Table combinations to see baseline data.

 
Others
 
- Microsoft Project 2010 : Performing a Schedule Reality Check - Baselining the Schedule
- Microsoft Visio 2010 : Adding Sophistication to Your Drawings - Working with background pages and borders
- Microsoft Visio 2013 : Adding Sophistication to Your Drawings - Managing pages and page setup
- Microsoft Excel 2013 : Checking Compatibility - Check Workbook Compatibility
- Microsoft Excel 2013 : Working with Accounts - Work with Online Accounts, Add Online Services
- Microsoft Excel 2013 : Saving a Workbook to Online Services - Save a Workbook to Online Storage
- Microsoft Excel 2013 : Saving a Workbook with Different Formats - Save a Workbook with Another Format
- Microsoft Excel 2013 : Saving a Workbook (part 2) - Save an Excel 97-2003 Workbook
- Microsoft Excel 2013 : Saving a Workbook (part 1) - Save a Workbook for Excel 2013
- Microsoft Excel 2013 : Getting Help While You Work - Use the Help Viewer to Get Answers, Search for Help, Use Local or Online Help
 
 
REVIEW
 
- First look: Apple Watch

- 10 Amazing Tools You Should Be Using with Dropbox

- Sigma 24mm f/1.4 DG HSM Art

- Canon EF11-24mm f/4L USM

- Creative Sound Blaster Roar 2

- Alienware 17 - Dell's Alienware laptops

- Smartwatch : Wellograph

- Xiaomi Redmi 2
 
Popular tags
 
Video Tutorail Microsoft Access Microsoft Excel Microsoft OneNote Microsoft PowerPoint Microsoft Project Microsoft Visio Microsoft Word Active Directory Biztalk Exchange Server Microsoft LynC Server Microsoft Dynamic Sharepoint Sql Server Windows Server 2008 Windows Server 2012 Windows 7 Windows 8 Adobe Indesign Adobe Flash Professional Dreamweaver Adobe Illustrator Adobe After Effects Adobe Photoshop Adobe Fireworks Adobe Flash Catalyst Corel Painter X CorelDRAW X5 CorelDraw 10 QuarkXPress 8 windows Phone 7 windows Phone 8 BlackBerry Android Ipad Iphone iOS
 
Top 10
 
- How To Install Windows Server 2012 On VirtualBox
- How To Fix Skype High CPU And Memory Usage In Windows 8
- Add 270 Additional Cleaning Options To CCleaner With CCEnhancer
- FPPT Provides More Than 2000 Free And Attractive PowerPoint Templates
- Setup Free Media Server To Stream Videos To DLNA Compatible TV, Xbox 360 & PS3 (Play Station 3)
- How To Install Android Market & Google Apps On Kindle Fire
- How To Make Ubuntu Look Like Windows 7
- How To Add A New Account in MS Outlook 2013
- Get Android & Mac OS X Style Gadgets For Windows 7 & Windows 8 With XWidget
- How To Activate Microsoft Office 2013
<