Microsoft Project 2010 : Entering Tracking Information at the Task Level (part 1)

3/29/2015 9:15:47 PM

Covers of this section how to employ to detect fields on the level of task to update the statute of task. It is how you would write progress manually, if you choose to employ this method.

This section looks at the following task-tracking fields:

  • Actual Start

  • Actual Finish

  • % Complete

  • Actual Duration

  • Remaining Duration

  • Actual Work

  • % Work Complete

  • Remaining Work

  • Time-Phased Work

You can view and edit most of these fields on the task by using the Gantt Chart view with the Tracking table columns showing (see Figure 1). To display the Tracking table in a task view, select the View tab, Tables, Tracking. To display the Work table in a task view, select the View tab, Tables, Work. You can edit the % Work Complete and Remaining Work fields, and you can enter time-phased work in the time-phased grid on the Task Usage view.

Figure 1. The task Tracking table gives you access to many of the fields needed for tracking progress at the task level.

Note

Keep in mind that Microsoft Project has different calculations for the “work” fields and the “%Complete” fields. By default, the %Work Complete for resource assignments and %Complete task fields are coupled such that an edit to either field updates the other field. You can decouple these two fields by selecting the File tab, Options, Schedule, and then clearing the Updating tasks status updates resource status check box. This means that it is possible to complete 100% of the work on a task and yet the % Complete for the duration field is not at 100%, but you then must manage each field individually for every task in the schedule.

 
Others
 
- Microsoft Project 2010 : Tracking Your Project’s Performance and Costs - Understanding the Fields Used in Updating the Project Schedule
- Microsoft Project 2010 : Tracking Your Project Progress - Working with Project Baselines (part 2) - Using Usage Views to Show Time-Phased Details
- Microsoft Project 2010 : Tracking Your Project Progress - Working with Project Baselines (part 1) - Viewing Baselines
- Microsoft Project 2010 : Performing a Schedule Reality Check - Baselining the Schedule
- Microsoft Visio 2010 : Adding Sophistication to Your Drawings - Working with background pages and borders
- Microsoft Visio 2013 : Adding Sophistication to Your Drawings - Managing pages and page setup
- Microsoft Excel 2013 : Checking Compatibility - Check Workbook Compatibility
- Microsoft Excel 2013 : Working with Accounts - Work with Online Accounts, Add Online Services
- Microsoft Excel 2013 : Saving a Workbook to Online Services - Save a Workbook to Online Storage
- Microsoft Excel 2013 : Saving a Workbook with Different Formats - Save a Workbook with Another Format
 
 
REVIEW
 
- First look: Apple Watch

- 10 Amazing Tools You Should Be Using with Dropbox

- Sigma 24mm f/1.4 DG HSM Art

- Canon EF11-24mm f/4L USM

- Creative Sound Blaster Roar 2

- Alienware 17 - Dell's Alienware laptops

- Smartwatch : Wellograph

- Xiaomi Redmi 2
 
Popular tags
 
Video Tutorail Microsoft Access Microsoft Excel Microsoft OneNote Microsoft PowerPoint Microsoft Project Microsoft Visio Microsoft Word Active Directory Biztalk Exchange Server Microsoft LynC Server Microsoft Dynamic Sharepoint Sql Server Windows Server 2008 Windows Server 2012 Windows 7 Windows 8 Adobe Indesign Adobe Flash Professional Dreamweaver Adobe Illustrator Adobe After Effects Adobe Photoshop Adobe Fireworks Adobe Flash Catalyst Corel Painter X CorelDRAW X5 CorelDraw 10 QuarkXPress 8 windows Phone 7 windows Phone 8 BlackBerry Android Ipad Iphone iOS
 
Top 10
 
- How To Install Windows Server 2012 On VirtualBox
- How To Fix Skype High CPU And Memory Usage In Windows 8
- Add 270 Additional Cleaning Options To CCleaner With CCEnhancer
- FPPT Provides More Than 2000 Free And Attractive PowerPoint Templates
- Setup Free Media Server To Stream Videos To DLNA Compatible TV, Xbox 360 & PS3 (Play Station 3)
- How To Install Android Market & Google Apps On Kindle Fire
- How To Make Ubuntu Look Like Windows 7
- How To Add A New Account in MS Outlook 2013
- Get Android & Mac OS X Style Gadgets For Windows 7 & Windows 8 With XWidget
- How To Activate Microsoft Office 2013
<