Microsoft Project 2010 : Setting Up Project for Your Use - Defining Environment Options (part 5)

12/11/2014 8:28:57 PM
Save Tab

The Save tab is where you define what kind of file you want your project to save as and where you want to save it (see Figure 8). You can also turn on the Auto Save feature to automatically save your project as you are working. We all know how a power outage can cause you to lose all your unsaved data; this feature is a great option to avoid that situation.

Figure 8. Use the Save tab of the Options window to define the default file type and location for saving your project files.

The Cache section refers to an instance of Project Professional that is linked to Project Server. The Cache stores a local copy of project files, allowing Project Server to download only the differences between the published file and the copy in the local Cache. The default of 50MB is plenty, unless you are opening a lot of large project files. Increase the size limit as your available hard drive space allows.

Language Tab

As the window describes itself, the Language tab (see Figure 9) enables you to add additional languages to edit your documents. In cases where you are working in a language that is different from your local installation of windows (for example, if you’ve brought your own laptop to a client site, and the client’s primary language is different from yours), you can set a different language priority order for Project.

Figure 9. The Language tab of the Options screen.

Advanced Tab

The Advanced tab (see Figure 10) is a grab-bag of remaining option sets that are used by a minority of managers. However, it’s likely that you will at some point need to make a change on this tab.

Figure 10. The Advanced tab of the Options screen.

The options in the General section are as follows:

  • Set AutoFilter on for New Projects— This refers to a small arrow that appears next to columns in views when this option is selected. Clicking this arrow brings up a sorting and grouping control.

  • Prompt for Project Info New Projects— This applies only to projects that are associated with a project server instance. When a new project is created, this opens a window allowing the user to enter data in project-level fields (managers can enter this data at any time, regardless).

  • Open Last File on Startup— If you are working with a single project file every day, this saves you the hassle of opening first Project and then the file.

  • Undo Levels— Although Undo is technically unlimited, it is practically limited by the amount of RAM your computer has. Managers that perform heavy future modeling (“what if-ing”) might want to increase this number.

The Project Web Access section also only applies to projects that are associated with an instance of Project Server.

The Planning Wizard section should be self-explanatory. Note, however, that there is some overlap with the Scheduling section on the Schedule tab in the Project Options screen.

The General Options for this project section enables you to set standard rates, but, more interestingly, it enables you to toggle Automatically Add New Resources and Tasks on and off. This feature is useful insofar as it prevents you from creating the same resource repeatedly with slight variations in name.

The Edit section should be self-explanatory, with the exception of the Ask to Update Automatic Links option. Project will ask before updating automatic links (if there are any) when a project is first opened. Automatic links can be made to Excel documents, and so on, just like any other Office application.

The Options in the Display section are as follows:

  • Show This Number of Recent Documents controls how many recent documents are tracked in the Open file dialog.

  • Show Status Bar refers to the bar running along the bottom of your Project window, where things such as the New Task Mode control and the Zoom control are displayed.

  • Show Windows in Task Bar refers to your Windows task bar and controls whether the task bar will display multiple windows for Project if you have multiple Project files open.

  • Use Internal IDs enables Project to ignore local names in favor of internal machine names. This is better left set to On in most circumstances, but there might be an instance where you need to control how Project matches things such as Views that you move with the Organizer, particularly if you don’t want to have items with duplicate names but different specifications.

  • Automatically Add New Views is very much a matter of preference. If you manage your projects in a consistent manner, it makes sense to turn this on. If each project you manage is totally unique, turn it off.

  • Show Scroll Bars is self-explanatory.

  • Show OLE Links Indicators is self-explanatory. OLE links are links from tasks to other Office applications.

  • Show Bars and Shapes is self-explanatory. You might want to turn this off if you are using a computer with a particularly weak graphics card.

The options in the Display options for this project section are mostly self-explanatory with the exception of the Show Project Summary task option. The Project Summary task is a zero-level task with the same name as the project file. It displays summary data for the entire project. Although this is off by default, most experienced Project users prefer to have it on.

The Earned Value Options for This Project Section options are as follows:

  • Default Task Earned Value Method— There are more than two Earned value methods specified in the ANSI Standard. % Complete—the default—isn’t one of them. Physical % complete is specified, however.

  • Baseline for Earned Value Calculation— This option enables you to use any of the baselines for calculating EV. This can be useful in a variety of scenarios, including situations where the project manager wants to control what appears on his s-curves.

The Calculation Options for This Project section options are as follows:

  • Move End of Completed Parts— This option causes Project to automatically “fix” completion dates that are in the future.

  • Move Start of Remaining Parts— This option reschedules un-started tasks with a start date in the past forward to the status date.

  • Edits to Total Task % Complete— By default, Project will spread actuals across the entire planned duration of a task. This results in actuals being recorded for future dates. Check this option to prevent creation of future-date actuals.

  • Calculate Multiple Critical Paths— This will not identify secondary and tertiary critical paths, which beg definition regardless. This will, however, calculate the critical paths for disconnected networks running through the same file.

  • Tasks Are Critical— Use this option to provide a little leeway in critical path calculation. On a longer project with larger duration tasks, the default of 0 days might not make sense.

 
Others
 
- Microsoft Project 2010 : Setting Up Project for Your Use - Defining Environment Options (part 4)
- Microsoft Project 2010 : Setting Up Project for Your Use - Defining Environment Options (part 3)
- Microsoft Project 2010 : Setting Up Project for Your Use - Defining Environment Options (part 2)
- Microsoft Project 2010 : Setting Up Project for Your Use - Defining Environment Options (part 1)
- Microsoft Visio 2013 : Creating a New Diagram - Replacing shapes
- Microsoft Visio 2013 : Creating a New Diagram - Using AutoAdd and AutoDelete
- Microsoft Visio 2013 : Creating a New Diagram - Identifying 1-D shapes and types of glue, Using AutoConnect and Quick Shapes
- Microsoft Visio 2013 : Creating a New Diagram - Connecting shapes with dynamic connectors
- Microsoft Access 2010 : Enhancing the Queries That You Build - Working with Outer Joins
- Microsoft Access 2010 : Enhancing the Queries That You Build - Creating Totals Queries
 
 
REVIEW
 
- First look: Apple Watch

- 10 Amazing Tools You Should Be Using with Dropbox

- Sigma 24mm f/1.4 DG HSM Art

- Canon EF11-24mm f/4L USM

- Creative Sound Blaster Roar 2

- Alienware 17 - Dell's Alienware laptops

- Smartwatch : Wellograph

- Xiaomi Redmi 2
 
VIDEO TUTORIAL
 
- How to create your first Swimlane Diagram or Cross-Functional Flowchart Diagram by using Microsoft Visio 2010 (Part 1)

- How to create your first Swimlane Diagram or Cross-Functional Flowchart Diagram by using Microsoft Visio 2010 (Part 2)

- How to create your first Swimlane Diagram or Cross-Functional Flowchart Diagram by using Microsoft Visio 2010 (Part 3)
 
Popular tags
 
Video Tutorail Microsoft Access Microsoft Excel Microsoft OneNote Microsoft PowerPoint Microsoft Project Microsoft Visio Microsoft Word Active Directory Biztalk Exchange Server Microsoft LynC Server Microsoft Dynamic Sharepoint Sql Server Windows Server 2008 Windows Server 2012 Windows 7 Windows 8 Adobe Indesign Adobe Flash Professional Dreamweaver Adobe Illustrator Adobe After Effects Adobe Photoshop Adobe Fireworks Adobe Flash Catalyst Corel Painter X CorelDRAW X5 CorelDraw 10 QuarkXPress 8 windows Phone 7 windows Phone 8 BlackBerry Android Ipad Iphone iOS
 
Top 10
 
- How To Install Android Market & Google Apps On Kindle Fire
- How To Make Ubuntu Look Like Windows 7
- How To Add A New Account in MS Outlook 2013
- Get Android & Mac OS X Style Gadgets For Windows 7 & Windows 8 With XWidget
- How To Activate Microsoft Office 2013
- How To Install Actual Facebook App On Kindle Fire
- How To Create, View And Edit Microsoft Office Files On Kindle Fire
- Download Attractive Business PowerPoint Templates For Free At SlideHunter
- How To Use And Enable Hibernate & Sleep Mode In Windows 8
- How To Get Microsoft Office 2013 Trial Product Key From Microsoft