Microsoft Project 2010 : Working with Resources - Adjusting Resource Calendars, Assigning Resources to Tasks

2/2/2015 3:14:53 AM

Adjusting Resource Calendars

An individual resource within your project may use a different calendar from the rest of the organization. For example, one of your project’s resources might be out on vacation for two weeks in the middle of July, or a specific piece of equipment might be available for reservation only on Mondays, Tuesdays, and Wednesdays each week. You can set a resource-specific calendar to accurately represent when that resource is able to work on your project.

To set a separate calendar for a resource, follow these steps:

1.
On the Project tab of the ribbon, in the Properties group, click Change Working Time.

2.
Click Create New Calendar.

3.
Choose how you want to create the resource’s calendar:

  • Create new base calendar— Click this option to create a new calendar for the resource, from scratch. Working times will be set to the calendar options from the Project Options dialog box, by default.

  • Make a copy of [existing base] calendar— Click this to use an existing base calendar as a starting point for the resource’s calendar. Use the drop-down list to choose which base calendar you want to copy.

4.
Type a name for the resource’s calendar in the Name box. You may want to use a name that helps to identify this as a calendar that is intended for use by a specific resource. This helps differentiate it from the base and task calendars for your project.

5.
Click OK to create the resource’s calendar.

6.
Similar to creating a base or task calendar, set the working days, nonworking days, default working times, and working times for specific time periods in the resource’s calendar.

7.
With the resource’s calendar set up and saved, on the View tab, in the Resource Views group, click Resource Sheet.

8.
Choose the calendar you just created in the Base Calendar column for the corresponding resource.

Assigning Resources to Tasks

After you add resources to your project, the next step is to assign them to tasks within your project.

Assigning a Resource Using the Task Information Dialog Box

You have a few different ways to assign work, material, and cost resources to tasks in your project. The Task Information dialog box provides a convenient location to identify details about the resource assignment, including the assignment owner and what percentage of the resource will be used for the task.

To assign a resource to a task in your project, follow these steps:

1.
In the Gantt Chart view, double-click the row for a task.

2.
Click the Resources tab on the Task Information dialog box.

3.
Click once in the first available row in the Resource Name column and use the drop-down list to select the resource you’re assigning to the task, as shown in Figure 1. This list is populated by the resources you have added to your project.

Figure 1. Click the name of the resource you are assigning in the Resource Name column.

If your organization has assignment owners who are separate from the project managers (for example, if your organization has a central resource manager for projects), type the resource’s assignment owner in the Assignment Owner column. This is a rare, advanced situation.


4.
Type a percentage in the Units column that represents how much of the resource’s time (or, if you’re assigning a material resource, units as identified in the Material Label column of the Resource Sheet view) will be spent on this task. For example, if a single resource is working half-time on this task and half-time on other tasks, type 50% in the Units column.

The Cost column is automatically populated using the information you entered for the resource in the Resource Sheet view. To view the populated Cost column, click OK on the Task Information dialog box and then double-click the task again to reopen it and see the calculated cost.


5.
Click OK to assign the resource to the task.

Assigning a Work Resource Using the Team Planner View

For work resources in your project, you can use the Team Planner view to assign tasks to specific people.

Here are the steps to follow to assign a task to a work resource using the Team Planner view:

1.
On the View tab, in the Resource Views group, click Team Planner.

2.
Click and drag a task listed under Unassigned Tasks up to a row in the time-scaled portion of the view for one of the work resources listed in the Resource Name column. When dragging the task, note that you can also adjust where the task falls horizontally in the time-scaled portion of the view. This will adjust the start and finish dates for the task and may result in a change in the constraint for the task.

3.
If you want to add another resource to a task that is already assigned to a work resource in the Team Planner view, double-click the task bar to open the Task Information dialog box.
 
Others
 
- Microsoft Project 2010 : Working with Resources - Understanding Resource Types and Other Factors, Adding Resources to Your Project
- Microsoft OneNote 2010 : Searching Notes (part 4) - Troubleshooting Problems with Search
- Microsoft OneNote 2010 : Searching Notes (part 3) - Searching for Text with the Search Results Task Pane
- Microsoft OneNote 2010 : Searching Notes (part 2) - Searching for Text on the Current Page, Searching for Text with Instant Search
- Microsoft OneNote 2010 : Searching Notes (part 1) - Turning Audio Search On or Off, Turning Text Recognition in Pictures On or Off
- Microsoft OneNote 2010 : Prioritizing and Categorizing Notes with Tags (part 2) - Search for Tagged Notes, Removing a Tag from a Note
- Microsoft OneNote 2010 : Prioritizing and Categorizing Notes with Tags (part 1) - Applying a Tag to a Note
- Microsoft OneNote 2010 : Organizing the Pages and Sections in a Notebook (part 2) - Moving or Copying a Notebook Section, Merging One Notebook Section into Another
- Microsoft OneNote 2010 : Organizing the Pages and Sections in a Notebook (part 1) - Displaying the Hierarchy of a Notebook on the Navigation Bar
- Microsoft OneNote 2010 : Navigating Notebook Content with Links (part 2) - Notebooks list or click the Open Notebook button. Creating Wiki-Style Links to Other Locations in Your Notebook
 
 
REVIEW
 
- First look: Apple Watch

- 10 Amazing Tools You Should Be Using with Dropbox

- Sigma 24mm f/1.4 DG HSM Art

- Canon EF11-24mm f/4L USM

- Creative Sound Blaster Roar 2

- Alienware 17 - Dell's Alienware laptops

- Smartwatch : Wellograph

- Xiaomi Redmi 2
 
VIDEO TUTORIAL
 
- How to create your first Swimlane Diagram or Cross-Functional Flowchart Diagram by using Microsoft Visio 2010 (Part 1)

- How to create your first Swimlane Diagram or Cross-Functional Flowchart Diagram by using Microsoft Visio 2010 (Part 2)

- How to create your first Swimlane Diagram or Cross-Functional Flowchart Diagram by using Microsoft Visio 2010 (Part 3)
 
Popular tags
 
Video Tutorail Microsoft Access Microsoft Excel Microsoft OneNote Microsoft PowerPoint Microsoft Project Microsoft Visio Microsoft Word Active Directory Biztalk Exchange Server Microsoft LynC Server Microsoft Dynamic Sharepoint Sql Server Windows Server 2008 Windows Server 2012 Windows 7 Windows 8 Adobe Indesign Adobe Flash Professional Dreamweaver Adobe Illustrator Adobe After Effects Adobe Photoshop Adobe Fireworks Adobe Flash Catalyst Corel Painter X CorelDRAW X5 CorelDraw 10 QuarkXPress 8 windows Phone 7 windows Phone 8 BlackBerry Android Ipad Iphone iOS
 
Top 10
 
- How To Install Android Market & Google Apps On Kindle Fire
- How To Make Ubuntu Look Like Windows 7
- How To Add A New Account in MS Outlook 2013
- Get Android & Mac OS X Style Gadgets For Windows 7 & Windows 8 With XWidget
- How To Activate Microsoft Office 2013
- How To Install Actual Facebook App On Kindle Fire
- How To Create, View And Edit Microsoft Office Files On Kindle Fire
- Download Attractive Business PowerPoint Templates For Free At SlideHunter
- How To Use And Enable Hibernate & Sleep Mode In Windows 8
- How To Get Microsoft Office 2013 Trial Product Key From Microsoft